PMI Agile Certified Practitioner (PMI-ACP) — Question 64

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
What should the project leader do?

Answer options

Correct answer: C

Explanation

The correct answer is C because it allows for customer input while also focusing on prioritization for future work, ensuring that the project can meet its deadlines. Options A and B restrict the feedback process, which may not align with customer needs, while D does not provide any structured approach to managing feedback and may lead to confusion.