PMI Agile Certified Practitioner (PMI-ACP) — Question 67
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
Answer options
- A. Collect stakeholder requirements
- B. Conduct an iteration planning meeting
- C. Communicate product backlog items to the stakeholders
- D. Facilitate a product development roadmap workshop
Correct answer: D
Explanation
Facilitating a product development roadmap workshop allows for direct collaboration and input from key stakeholders, ensuring their engagement in the planning process. While collecting requirements, conducting meetings, and communicating backlog items are valuable, they do not provide the same level of interactive involvement as a workshop.