PMI Agile Certified Practitioner (PMI-ACP) — Question 5
An organization initiates a pilot project to introduce agile methodology for the successful delivery of projects.
What should the project manager do to share this project's knowledge and learning with wider organizational business groups?
Answer options
- A. Invite people from across the organization to attend daily stand ups
- B. Invite people from across the organization to attend retrospectives
- C. Invite people from across the organization to attend the release meeting and project retrospectives
- D. Regularly meet with people across the organization to share the project's lessons learned and best practices
Correct answer: D
Explanation
The correct answer is D because regularly meeting with individuals across the organization allows for a structured sharing of lessons learned and best practices, which is crucial for fostering a culture of continuous improvement. Options A, B, and C focus on specific meetings that may not provide comprehensive insights into the overall project experiences and learnings.