PMI Agile Certified Practitioner (PMI-ACP) — Question 4
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities.
What should the agile project manager do?
Answer options
- A. Provide both project teams with the highest priority needs
- B. Request the project team's questions in writing prior to the next meeting
- C. Facilitate a meeting with each team and the product owner to finds a solution
- D. Provide both teams with each project's documentation
Correct answer: C
Explanation
The correct answer is C because facilitating a meeting allows for direct communication between the product owner and the teams, enabling them to clarify requirements and priorities collaboratively. Option A only addresses priority needs without resolving misunderstandings, B delays addressing questions, and D does not ensure the teams fully understand the documentation.