PMI Agile Certified Practitioner (PMI-ACP) — Question 6
During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks, which has lowered motivation.
What should the agile practitioner do?
Answer options
- A. Organize a team-building activity to improve team morale
- B. Have team members work in pairs to learn from each other and develop new skills
- C. Ask team members to perform a value stream analysis of their activities
- D. Add more resources to the team to help with tasks
Correct answer: C
Explanation
The correct answer is C because conducting a value stream analysis can help identify inefficiencies and areas for improvement in their processes. Option A, while beneficial for morale, does not address the root cause of the issue. Option B focuses on skill development but may not alleviate the repetitive tasks. Option D may provide temporary relief but does not solve the underlying problem of task redundancy.