PMI Agile Certified Practitioner (PMI-ACP) — Question 338

When prioritizing features to be delivered in an iteration, on what should an agile team defer work?

Answer options

Correct answer: C

Explanation

The correct answer is C: Low-risk and low-value features are often deprioritized because they do not significantly contribute to the overall value of the project. In contrast, high-risk and high-value items (A) and low-risk and high-value items (D) should be prioritized due to their potential impact, while high-risk and low-value items (B) are also not worth pursuing at the moment.