PMI Agile Certified Practitioner (PMI-ACP) — Question 337
Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.
What should the team do?
Answer options
- A. Conduct frequent demos and obtain feedback from users throughout the development of the next release
- B. Inform senior management that since the product was successfully released, the project is considered delivered and should be closed
- C. Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity
- D. Implement a better definition of done to ensure that continuous integration processes are managed effectively
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of continuous user feedback which is crucial for enhancing product value. Option B incorrectly suggests closing the project after a successful release, while option C focuses on scaling teams rather than directly improving product value. Option D, while useful, does not directly address the need for user feedback and engagement in the development process.