PMI Agile Certified Practitioner (PMI-ACP) — Question 339

Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.
What should the agile team do?

Answer options

Correct answer: A

Explanation

The correct answer is A because creating a central repository allows Team B to access the necessary information consistently and independently, facilitating their work. Options B and C are less effective as they do not provide exclusive access to the information needed by Team B. Option D is not ideal since it relies on Team B to ask for information rather than providing it proactively.