PMI Agile Certified Practitioner (PMI-ACP) — Question 243
Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?
Answer options
- A. Use an information radiator to help increase the transparency of work for key stakeholders.
- B. Send status updates whenever the stakeholders request them.
- C. Hold Scrum meetings more frequently to ensure stakeholders are well informed.
- D. Instruct the team to focus on their own assignments rather than the work of others.
Correct answer: A
Explanation
The correct answer is A because using an information radiator improves transparency, allowing stakeholders to see real-time updates on work status. Options B and C rely on intermittent communication, which may not be as effective in providing timely updates. Option D undermines collaboration and transparency among team members, which is essential in Agile environments.