PMI Agile Certified Practitioner (PMI-ACP) — Question 243

Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because using an information radiator improves transparency, allowing stakeholders to see real-time updates on work status. Options B and C rely on intermittent communication, which may not be as effective in providing timely updates. Option D undermines collaboration and transparency among team members, which is essential in Agile environments.