PMI Agile Certified Practitioner (PMI-ACP) — Question 244

A team member has made a mistake on a project. How should the scrum master address the mistake?

Answer options

Correct answer: C

Explanation

The correct answer is C because conducting a retrospective allows the team to reflect on the mistake and discuss ways to improve processes and avoid similar issues in the future. Options A and B focus on enforcing rules rather than addressing the root cause, while D promotes competition rather than collaboration, which is not conducive to a healthy team environment.