PMI Agile Certified Practitioner (PMI-ACP) — Question 203

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

Answer options

Correct answer: C

Explanation

The correct answer is C because facilitating team brainstorming helps identify and document risks associated with technical complexity, which is crucial for managing them effectively. Options A and B focus on training and initial risk mitigation but do not engage the team in the risk identification process. Option D, while promoting innovation, does not address the immediate need to recognize and register risks arising from complexity.