PMI Agile Certified Practitioner (PMI-ACP) — Question 202
A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?
Answer options
- A. Discuss the issue to reduce the backlog based on decreased productivity of the team.
- B. Collect updates from each team member before the meeting and share them with all members.
- C. Ask the team member to update daily progress on the information radiators.
- D. Change the team velocity to show positive progress in shared information radiators.
Correct answer: C
Explanation
The correct answer is C because asking the team member to provide daily updates on the information radiators allows for visibility and accountability, which can help keep the team informed. Option A does not address the immediate issue, option B may lead to miscommunication, and option D falsely represents the team's performance, which could lead to further problems.