PMI Agile Certified Practitioner (PMI-ACP) — Question 177

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope, the team plans to work only on spike user stories for the next three sprints.
What should an agile coach do in this situation?

Answer options

Correct answer: C

Explanation

The correct answer is C because it encourages the team to make progress on high-priority user stories while still addressing unknowns through spikes. Options A and B focus on risk identification and funding, which do not directly aid in advancing project deliverables. Option D, while supportive of the spikes, does not address the need to prioritize user stories that can provide value sooner.