PMI Agile Certified Practitioner (PMI-ACP) — Question 178

A scrum master would like to provide information to key stakeholders on the daily resource and project activities.
Which tool should the Scrum master use to provide these updates?

Answer options

Correct answer: D

Explanation

The Iteration burndown chart is the most suitable tool for providing daily updates on the progress of the project, as it visually represents the amount of work remaining in an iteration. The other options, while useful for different purposes, do not specifically focus on daily progress tracking for stakeholders.