PMI Agile Certified Practitioner (PMI-ACP) — Question 176

During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet most pressing needs and provide value.
What should the team have done to prevent this?

Answer options

Correct answer: A

Explanation

The correct choice, A, emphasizes the importance of prioritizing requirements before starting iteration work, ensuring that the most valuable features are addressed first. Option B is incorrect because stability in requirements does not guarantee they meet stakeholder needs. Option C does not address the initial requirements and their alignment with stakeholder expectations. Option D, while important, does not directly relate to the prioritization of requirements.