PMI Agile Certified Practitioner (PMI-ACP) — Question 174
An agile team is preparing a release plan for a project.
What information will the team need to complete this plan?
Answer options
- A. Amount of work needed to complete a single user story
- B. Amount of work that can be accomplished by each team member
- C. Amount of work that can be accomplished in an iteration
- D. Amount of work that can be accomplished by the entire team
Correct answer: C
Explanation
The correct answer is C because the team needs to know how much work can be completed within a single iteration to effectively plan the release. Options A and B focus on individual components rather than the overall iteration capacity, while option D, although related, does not specify the time frame of an iteration.