PMI Agile Certified Practitioner (PMI-ACP) — Question 173

A team member on a scrum project previously provided support to another application. Due to this with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes these issues in the risk register.
What should the scrum master do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because it is essential for the scrum master to communicate and address the identified risks to ensure the team's focus and productivity. Option A is incorrect as multitasking can lead to diminished quality and focus. Option B does not resolve the risk issue and may not be feasible, while option D might hinder the team's progress by limiting the work they can accomplish.