On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product.
How should this be addressed?

Answer options

Correct answer: D

Explanation

The correct answer is D because having the product owner explain the product vision and review the release plan helps the team understand the larger context of their tasks and user stories. The other options focus on internal team discussions or retrospective actions, which may not provide the necessary clarity on the overall product direction.