PMI Agile Certified Practitioner (PMI-ACP) — Question 129
There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story.
Who should the Scrum Master invite to the meeting?
Answer options
- A. The core team and the customer
- B. The product owner and key stakeholders
- C. The customer and the sponsor
- D. The core team and the product owner
Correct answer: D
Explanation
The correct answer is D because the core team and the product owner are directly involved in the development and prioritization of the features. Options A, B, and C include individuals who, while important, are not as critical to the immediate technical discussions needed to complete the story.