PMI Agile Certified Practitioner (PMI-ACP) — Question 131
An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.
What should the agile team do?
Answer options
- A. Evaluate how much can be delivered based on the Scrum Master's estimation
- B. Identify a set of user stories based on the team's velocity
- C. Initiate an estimation session
- D. Consult historical data for project completion
Correct answer: C
Explanation
The correct action is to initiate an estimation session, as this allows the team to collaboratively assess the complexity and effort required for the stories, leading to a more accurate delivery timeline. The other options do not directly involve the entire team in creating estimates, which is essential for Agile practices and accurate planning.