PMI Agile Certified Practitioner (PMI-ACP) — Question 125
On what should an agile team work to achieve predictable flow?
Answer options
- A. Small user stories
- B. Simple acceptance criteria
- C. Lean features
- D. Lean backlogs
Correct answer: A
Explanation
An agile team should work on small user stories as they enable better estimation, quicker feedback, and more manageable tasks, leading to a predictable flow. While simple acceptance criteria, lean features, and lean backlogs are important, they do not directly contribute to the predictability of the team's workflow as effectively as small user stories do.