PMI Agile Certified Practitioner (PMI-ACP) — Question 126

Following an upgrade, a software support team is overwhelmed by the number of tickets being submitted by end users. The team's manager is pushing the team to `work smart` by focusing on activities that deliver the most value in the least amount of time.
What should the team do?

Answer options

Correct answer: C

Explanation

The correct answer, C, suggests that the team should first analyze the backlog to identify and resolve systematic issues, which can reduce future tickets. Options A and B do not address the underlying problems and only prolong the situation, while D might not be a sustainable solution if the root cause of the tickets is not addressed.