PMI Agile Certified Practitioner (PMI-ACP) — Question 124

During an iteration planning meeting, the team suggests changes to add product vale that will require extra work and impact the schedule.
What should the agile project leader do?

Answer options

Correct answer: D

Explanation

The correct answer is D because the product owner has the authority to approve changes that impact the project scope and schedule. Options A and B do not address the need for product owner approval, while C could lead to scope creep without proper authorization.