PMI Agile Certified Practitioner (PMI-ACP) — Question 124
During an iteration planning meeting, the team suggests changes to add product vale that will require extra work and impact the schedule.
What should the agile project leader do?
Answer options
- A. Re-estimate the project
- B. Finish the product as it was initially planned
- C. Try to include as many changes as possible
- D. Ask the product owner for approval to proceed
Correct answer: D
Explanation
The correct answer is D because the product owner has the authority to approve changes that impact the project scope and schedule. Options A and B do not address the need for product owner approval, while C could lead to scope creep without proper authorization.