Program Management Professional (PgMP) — Question 61

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

Answer options

Correct answer: C

Explanation

The correct answer, C, is appropriate as it involves direct communication with both sponsors and the steering committee to collaboratively resolve their differences using the market analysis. Options A and B focus on internal processes without directly addressing the sponsors' conflict, while option D, while helpful, does not prioritize a direct conflict resolution meeting with all parties involved.