Program Management Professional (PgMP) — Question 60
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product's delivery time.
What should the program manager update first?
Answer options
- A. Procurement management plan
- B. Benefits register
- C. Risk register
- D. Benefits management plan
Correct answer: B
Explanation
The program manager should update the Benefits register first because the reduction in delivery time directly impacts the project's benefits. The other options, while important, do not specifically address the immediate impact of the trade agreement on the project's benefits.