Program Management Professional (PgMP) — Question 40

A program sponsor is concerned about the status of high-priority risks and budget variances.
The program manager should refer to which of the following?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the program status dashboard provides a visual representation of the current status of risks and budget, making it ideal for quick updates. The other options, while relevant, do not focus specifically on the real-time status of high-priority risks and budget variances as effectively as the dashboard.