Program Management Professional (PgMP) — Question 40
A program sponsor is concerned about the status of high-priority risks and budget variances.
The program manager should refer to which of the following?
Answer options
- A. Program status dashboard
- B. Program management plan
- C. Program performance report
- D. Program management information system (PMIS)
Correct answer: A
Explanation
The correct answer is A, as the program status dashboard provides a visual representation of the current status of risks and budget, making it ideal for quick updates. The other options, while relevant, do not focus specifically on the real-time status of high-priority risks and budget variances as effectively as the dashboard.