Program Management Professional (PgMP) — Question 388

A program stakeholder is questioning the benefits and performance of a program. Which documents should the program manager share with this stakeholder to demonstrate the program value delivered?

Answer options

Correct answer: C

Explanation

The correct answer is C because the program business case outlines the rationale for the program, while the program benefits register lists the expected benefits, and program performance reports provide evidence of progress and success. Options A and B do not include the business case, which is crucial for demonstrating overall value, while option D includes documents that do not directly relate to program benefits or performance.