A program steering committee has initiated an 8-year overseas infrastructure construction program. This program will compliment several other overseas programs already underway. The three key engineers have already been assigned to other programs and are unavailable to commit to the new program.

What should the program manager do?

Answer options

Correct answer: B

Explanation

The best course of action is to report the gap to the program sponsor and collaborate to find a solution, as this fosters communication and teamwork. Option A focuses on recruitment without addressing the immediate issue. Option C suggests training and recruitment but does not involve the program sponsor in resolving the gap. Option D disregards the busy schedules of the engineers, which could disrupt other projects.