Program Management Professional (PgMP) — Question 370

A financial company is transitioning to a new billing system and is approaching completion. Before the transition starts, a mandatory requirement must be met to check on some program performance metrics. To address this requirement, a phase-gate review has been scheduled for the following month.

In preparation for this important review, what can the program manager do to ensure the program is on track to meet the requirements?

Answer options

Correct answer: A

Explanation

The correct answer is A because reviewing key performance indicators (KPIs) will provide insight into the program's current performance against its objectives. The other options focus on governance or benefits management, which are less directly related to assessing immediate program performance metrics.