Program Management Professional (PgMP) — Question 354
The program manager completed the program's benefits analysis and planning activities.
What will this ensure for the program?
Answer options
- A. Information necessary to establish key benefit performance indicators
- B. A transition plan to facilitate the ongoing realization of benefits
- C. A plan to monitor performance due to operational, financial, and benefits changes
- D. A benefits management plan to guide the work through the remainder of the program
Correct answer: A
Explanation
Choosing option A is correct because completing the benefits analysis and planning activities provides the essential information required to create key performance indicators for measuring benefits. Options B, C, and D, while related to benefits management, do not directly result from the benefits analysis and planning activities completed by the program manager.