Program Management Professional (PgMP) — Question 353
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress?
Answer options
- A. Define the key performance indicators (KPIs) for the program's outcome.
- B. Invite the key stakeholder to review the program charter and the program objectives.
- C. Provide additional program performance reports to the key stakeholder.
- D. Maintain the benefits register and provide it to the key stakeholder.
Correct answer: C
Explanation
The correct answer is C because providing additional program performance reports offers concrete evidence of progress against objectives. Options A and B are proactive steps but do not directly show current progress. Option D, while useful for tracking benefits, does not specifically address the stakeholder's request for progress demonstration.