Program Management Professional (PgMP) — Question 355

A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board.
What should the program manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because obtaining approval from the sponsoring organization is essential before starting the closeout procedures and ensuring benefits are sustained by the supporting organization. Options A, B, and C are important tasks but occur later in the process and do not directly follow the presentation of benefits.