Program Management Professional (PgMP) — Question 338

A company very new to program management is working on a pilot program. The program manager of this pilot program will encounter many improvement opportunities throughout the program life cycle.

How should the program manager address the need for continuous improvement throughout this pilot program?

Answer options

Correct answer: C

Explanation

The correct answer is C because regularly reviewing and updating the program management plan ensures that the program adapts and improves over time based on new insights. Options A and B do not focus on continuous improvement within the current pilot, and option D, while important, pertains specifically to governance rather than the broader program management processes.