Program Management Professional (PgMP) — Question 338
A company very new to program management is working on a pilot program. The program manager of this pilot program will encounter many improvement opportunities throughout the program life cycle.
How should the program manager address the need for continuous improvement throughout this pilot program?
Answer options
- A. Initiate a second pilot program to utilize the lessons learned from this pilot program
- B. Ensure that the updated processes are implemented in the proposed program management office (PMO).
- C. Review and update the program management plan regularly with process- related updates
- D. Review and update the program governance plan regularly with process- related updates
Correct answer: C
Explanation
The correct answer is C because regularly reviewing and updating the program management plan ensures that the program adapts and improves over time based on new insights. Options A and B do not focus on continuous improvement within the current pilot, and option D, while important, pertains specifically to governance rather than the broader program management processes.