Program Management Professional (PgMP) — Question 320

A program manager for a sustainability program that aims to reduce carbon emissions and waste generation has implemented a program-level continuous improvement process that involves engaging stakeholders, benchmarking performance, and implementing best practices. The program manager encountered some resistance and challenges from some of the key stakeholders who were reluctant to change their behaviors and processes.

What should the program manager do next to address these challenges?

Answer options

Correct answer: C

Explanation

The correct answer is C, as it involves reassessing the stakeholder analysis and communication plan, which can help identify specific concerns and barriers to change, fostering better engagement. Options A and B may not address the root of the resistance directly, while D could escalate the situation unnecessarily without first attempting to resolve the issues through improved communication.