Program Management Professional (PgMP) — Question 319
A program manager has taken over a program in progress for several years. During a program governance review, the new program manager realizes that several projects do not have key performance indicators (KPIs).
What should the program manager do?
Answer options
- A. Develop a benefits management plan
- B. Align the benefits with the strategic objectives
- C. Ensure that the projects are delivering value
- D. Develop a key performance indicator dashboard
Correct answer: D
Explanation
The correct answer is D because developing a key performance indicator dashboard allows the program manager to establish measurable criteria for evaluating project performance. Options A and B focus on benefits management and alignment with strategic objectives but do not directly address the lack of KPIs. Option C, while important for project value, does not provide a systematic approach to tracking performance.