Program Management Professional (PgMP) — Question 311

A program has had a history of difficulties reaching agreements on scope priorities among its agile component projects. What should the program manager do proactively to help resolve this unproductive pattern?

Answer options

Correct answer: C

Explanation

The correct answer is C because negotiating with product owners and agile teams directly addresses the misalignment of objectives and helps ensure everyone is on the same page. Option A focuses on decision-making but does not directly address the need for alignment, while B suggests mediation, which may not resolve the underlying issues. Option D, creating a stakeholder engagement matrix, is useful but does not directly tackle the priority disagreements among projects.