Program Management Professional (PgMP) — Question 312

A program is in the formulation phase. A program manager needs to document major program milestones that highlight the realized benefits for the stakeholder community.

Which document should the program manager reference to create this artifact?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Benefits Management Plan and Register specifically outline the anticipated benefits and milestones associated with a program, providing a clear framework for documenting stakeholder achievements. The other options, while related to scheduling and project management, do not specifically focus on benefits realization for stakeholders.