Program Management Professional (PgMP) — Question 312
A program is in the formulation phase. A program manager needs to document major program milestones that highlight the realized benefits for the stakeholder community.
Which document should the program manager reference to create this artifact?
Answer options
- A. Program integrated master schedule
- B. Roll up of component project schedules
- C. Benefits management plan and register
- D. Program schedule management plan
Correct answer: C
Explanation
The correct answer is C because the Benefits Management Plan and Register specifically outline the anticipated benefits and milestones associated with a program, providing a clear framework for documenting stakeholder achievements. The other options, while related to scheduling and project management, do not specifically focus on benefits realization for stakeholders.