Program Management Professional (PgMP) — Question 295

The program sponsor requests that a junior project manager take over a complex component project as a professional development opportunity. The component project currently has several senior subject matter experts (SMEs) working on it and also has dependencies with other large projects to deliver key benefits to the organization.

The junior project manager is both excited and concerned about the assignment and decides the best next step is to:

Answer options

Correct answer: B

Explanation

The correct answer, B, is appropriate because it allows the junior project manager to view the assignment as a developmental opportunity while also seeking mentorship from an experienced senior project manager. Option A, while proactive, does not take advantage of the learning opportunity. Option C is premature as it suggests starting work without proper preparation, and option D indicates a lack of confidence and willingness to take on new challenges.