Program Management Professional (PgMP) — Question 283
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
Answer options
- A. Program performance report
- B. Communications management plan
- C. Communications log updates
- D. Information gathering and retrieval system
Correct answer: A
Explanation
The Program performance report is specifically designed to convey comprehensive status information, including program progress and cost details. The other options do not focus on providing such detailed status reports; the Communications management plan is about managing communication strategies, the Communications log updates track communication events, and the Information gathering and retrieval system is more about data management rather than reporting status.