Program Management Professional (PgMP) — Question 280

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Program scope statement, as it specifically outlines the scope and boundaries of the program, including deliverables. The other options, while related to program management, either focus on governance (B), management plans (A), or task breakdowns (D), which do not directly capture the defined scope.