Program Management Professional (PgMP) — Question 265
You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?
Answer options
- A. Materials required by the program
- B. Equipment your program uses
- C. Susan the application developer in your program
- D. Stakeholder identification
Correct answer: D
Explanation
The correct answer is D, as stakeholder identification is typically a one-time process that occurs at the beginning of a project or program. In contrast, materials, equipment, and personnel such as application developers require ongoing monitoring and control throughout the program's lifecycle.