Program Management Professional (PgMP) — Question 266
Which of the following is not a template element that is designed to make the project more effective?
Answer options
- A. Description of the work packages
- B. Required resources and skills
- C. Required actions to complete the project scope
- D. Contract file
Correct answer: D
Explanation
The correct answer is D, as a contract file is not a template element aimed at improving project effectiveness. In contrast, options A, B, and C are all essential components that provide structure and clarity, facilitating better project management.