Program Management Professional (PgMP) — Question 257
You are the program manager for the NHQ Program. Your program has a budget of
$4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?
Answer options
- A. The customer must now sign the program scope.
- B. The customer must now sign the payment for the program work.
- C. The customer must now sign the certificate of program closure.
- D. The customer must now sign the operational transfer agreement.
Correct answer: C
Explanation
The correct answer is C, the certificate of program closure, which is a formal document indicating that the program has been completed and all deliverables have been met. Options A and D pertain to different aspects of program management, while B relates to financial transactions rather than closure documentation.