Program Management Professional (PgMP) — Question 256
Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?
Answer options
- A. Program constraints
- B. Program scope
- C. High-level objectives for the program
- D. Project scope statement for all projects within the program
Correct answer: D
Explanation
The program charter includes elements like program constraints, program scope, and high-level objectives, which are essential for defining the program's overall vision. However, the project scope statement for individual projects falls outside the purview of the program charter, as it pertains to the specifics of each project rather than the program as a whole.