Program Management Professional (PgMP) — Question 255
You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?
Answer options
- A. A forklift
- B. Materials for the installation of a new server
- C. A positive risk response
- D. Gary, an application developer
Correct answer: C
Explanation
A positive risk response is a strategy for managing risks and does not represent a tangible resource that can be allocated to a program. In contrast, a forklift, materials for server installation, and an application developer like Gary are all physical or human resources essential for program execution.