Program Management Professional (PgMP) — Question 258
You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?
Answer options
- A. Certificate of completion
- B. Proposal agreement
- C. Invoice
- D. Contract
Correct answer: A
Explanation
The correct answer is A, the Certificate of completion, which formally acknowledges that the vendor has completed the work as per the contract. The other options, such as the Proposal agreement and Contract, are not appropriate as they pertain to initial agreements, while an Invoice is related to payment rather than work completion acknowledgment.