Program Management Professional (PgMP) — Question 245

A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?

Answer options

Correct answer: D

Explanation

The correct answer is D because the qualified seller list is utilized to issue requests for proposals (RFPs) to potential vendors. Options A and B are related to planning and preparing documents but do not directly involve the action of outsourcing. Option C pertains to budget management, which is not the immediate use of the qualified seller list.