Program Management Professional (PgMP) — Question 246

A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?

Answer options

Correct answer: A

Explanation

The correct answer is A, the Risk register, as it is specifically meant for documenting identified risks and their status. The other options, while related to risk management, do not serve as the primary documentation tool for recorded risks.