Program Management Professional (PgMP) — Question 236
The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.
What should the program manager do next?
Answer options
- A. Update the program benefits management plan and risk register.
- B. Implement the mitigation plan for the identified risk.
- C. Adjust the program scope to avoid the risk.
- D. Document the risk and create a mitigation plan.
Correct answer: D
Explanation
The correct answer is D because documenting the risk and creating a mitigation plan is essential to manage and address the risk effectively. Options A and B are premature as the program manager needs to first document the risk before updating plans or implementing responses. Option C is not appropriate as adjusting the scope may not always be feasible or necessary.