Program Management Professional (PgMP) — Question 235

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Answer options

Correct answer: A

Explanation

Change requests are typically a result of adjustments needed rather than a tool for control, making them unhelpful in the actual monitoring process. On the other hand, performance reports, forecasts, and earned value management provide insights and metrics essential for effective schedule control.